Foreman 3.4 Schedule and Planning

Hello,

With 3.3.0 GA coming soon, it’s time to talk about the 3.4 timelines and schedule,

The 3.3 branched on May 10th, and to keep up our 3-month release cadence that would mean we should branch for 3.4 on August 9th.

  • As before, we will be doing a stabilization week prior to branching to ensure we have working nightlies when branching.
  • Larger changes should be merged as early as possible in the release cycle, to ensure enough time to fix bugs prior to branching.
  • Keep in mind that installer module changes should also be merged prior to the stabilization week.
  • As we near the branching date, we shall ask your cooperation in focusing more on stabilizing and bug fixing and less on new features.
Event Date Day
3.4 Dev start 11th May Wednesday
3.4 Half way point 24th June Friday
3.4 Installer modules release week 25th to 29th July
3.4 Stabilization week 1st to 5th August
3.4 Branching 9th August Tuesday
3.4 RC1 11th August Thursday
3.4 RC2 25th August Thursday
3.4.0(GA) 8th September Thursday

If you have a significant change that you wish to get into 3.4, request to set the “Target Version” field on Redmine at least for the main tracker for the bug. We also request maintainers to make sure that when merged, any major features are added to the “highlighted features” section on the manual, and any deprecation or changes in behavior are also added to the relevant sections. If you wish to discuss any plans, this post’s comments can and should be used for that.

The versions of plugins and tools which are planned to be compatible with Foreman 3.4, request to add which you are aware about,

Hammer 3.4
Katello 4.6
Discovery 
Bootdisk 
Puppet 
Remote Execution
Statistics 
Tasks 
OpenSCAP
Ansible
Templates