During this week the installer team should make sure the Puppet modules are released so we’re ready for Foreman 3.7 stabilization week. For more information, see the schedule:
Following Foreman 3.6 GA, it’s time to look to 3.7.
Foreman 3.6 branched on 2023-02-21. We add 3 months of development time to that, so we end up with 2023-05-23 as the branching date with GA following 4 weeks later on 2023-06-20.
Working our way backwards from GA. As always, there are 2 release candidates prior to GA with 2 weeks between them. That’s preceded by branching (same day as RC1) and a week of stabilization. Installer modules should be done the week before stabilization.
Filling in…