Hello community,
The branching of Katello 4.4 is underway and we’re soon to begin unleashing Katello 4.4 release candidates. The target date for Foreman is February 14th, so that is our target for RC1 as well. The release process is below:
Roles
When Ready to Release
Release Owner
-
Request Hammer CLI Katello release from maintainers
-
Request Virt Who Configure release from maintainers
-
Request any other releases as needed from the release owners (consult the
:repos:
section ofconfigs/katello/4.4.yaml
) -
Change Redmine version 4.4.0.rc1 state to Closed
→ Not until 4.4.0 is GA’d. -
Do Cherry-picks: Clone tool_belt
-
If any minor versions of Katello have been added to Redmine since the last cherry-pick, make sure to include them in
prior_releases
in configs/katello/4.4.yaml -
Run
./tools.rb setup-environment configs/katello/4.4.yaml
-
Run
./tools.rb cherry-picks --version 4.4.0.rc1 configs/katello/4.4.yaml
- Open a PR in Katello release branch. Make sure the PR name starts with [CP] to prevent our automations from adding it to Redmine issues.
-
Using
git cherry-pick -x
as needed, verify tickets in the cherry_picks_4.4.0.rc1 file are accounted for, or additionally cherry-pick them. Recommended: Do this in tool_belt’s checkout of Katello, inrepos/katello/4.4.0.rc1/katello
. This way when you run cherry-picks again, tool_belt will be aware of any picks already completed. -
For any cherry-picks that are not needed (including Redmine trackers) you can add them to the
:ignores:
section oftool_belt
inconfigs/katello/4.4.yaml
-
If any minor versions of Katello have been added to Redmine since the last cherry-pick, make sure to include them in
-
Check for outdated deprecation warnings in the current and next release with
./tools check-deprecation-warnings configs/katello/4.4.yaml
. Follow the instructions in the output of the command. Don’t forget to create any Redmine issues needed! -
Bump version:
-
Open a PR (or use cherry-pick PR) against the release branch which updates
lib/katello/version.rb
to 4.4.0.rc1 -
git pull
to make sure you have the latest changes -
Commit:
git commit -m "Release 4.4.0.rc1"
-
Ensure that the commit above is the last commit and there are no commits after it. This is the commit that will get tagged. (Rearrange commits with
git rebase -i
if needed.)
-
Open a PR (or use cherry-pick PR) against the release branch which updates
-
Once the PR is merged, perform the following in the Katello release branch (the real one, not your fork):
-
Tag:
git tag -s -m "Release 4.4.0.rc1" 4.4.0.rc1
-
Push:
git push --follow-tags
(Must be pushed directly to the release branch, as pull request merges will not preserve tags.) -
Generate source gem:
gem build katello.gemspec
- Ensure you have a working login and password at rubygems.org
-
Push gem:
gem push katello-4.4.0.rc1.gem
-
Tag:
-
Inform the delivery team that the gem is published
Once Source is Available
Note it is considered good practice to release on a day when the next day is a working day. This means no releases on Fridays or on the day before a holiday.
Release Engineer
- Update release version similar to here
-
Update
katello
,katello-repos
andrubygem-katello
- Merge packaging PR once job is green
- Wait for Jenkins to build the packages (replace 4.4 with the matching Foreman version)
- Download, sign, upload RPM signatures and upload RPMs
- Kick off the release pipeline by calling release_pipeline
Once release is out
Release Owner
-
Confirm response that the build succeeded (or if necessary, do more cherry-picks and version bumps repeating the steps above)
-
Post a release announcement
-
Create and upload release specific developer stable box- Not until 4.4 is fully-released.